Question: Activit y Predecess or Norma l Time Norma l Cost Cras h Time Cras h cost Max cras h time Cost slop e A- 350270120
| Activit y | Predecess or | Norma l Time | Norma l Cost | Cras h Time | Cras h cost | Max cras h time | Cost slop e |
A- 350270120 BA 6804160240 CA 1060990130 DA 11507150425 EB 81006160230
F C,D 5 40 G E,F 670
4 70 1 30 6 70 - -
Total 450
FIND THE LEAST COST SCHEDULE IF
INDIRECT COSTS:
Project Duration 25 24 23
22 21
Indirect cost 400 350 300
250 200
Draw the project network as per the given predecessor relationship
Draw either AOA or AON diagram
Carryout forward pass and backward pass calculations
Identify the critical path and project duration