Question: activities prequisitions durations A - 2 B - 6 C - 4 D A 3 E C 5 F A 4 G B, D, E

activities

prequisitions

durations

A

-

2

B

-

6

C

-

4

D

A

3

E

C

5

F

A

4

G

B, D, E

2

Show the completion time, critical path and slack times via Activities-on-Arc (AOA).

When there is overtime situation, each activity is completed 1/4 of its normal duration early. But, the overtime wages are 1.5 times the daily normal wage of 100 $, i.e. 150 $. At the same time, increasing the project completion cost by 2/5 at the most is also allowed. If you exercise this, does the new completion times, critical path and activity costs change and how?