Question: activities prequisitions durations A - 2 B - 6 C - 4 D A 3 E C 5 F A 4 G B, D, E
| activities | prequisitions | durations |
| A | - | 2 |
| B | - | 6 |
| C | - | 4 |
| D | A | 3 |
| E | C | 5 |
| F | A | 4 |
| G | B, D, E | 2 |
Show the completion time, critical path and slack times via Activities-on-Arc (AOA).
When there is overtime situation, each activity is completed 1/4 of its normal duration early. But, the overtime wages are 1.5 times the daily normal wage of 100 $, i.e. 150 $. At the same time, increasing the project completion cost by 2/5 at the most is also allowed. If you exercise this, does the new completion times, critical path and activity costs change and how?