Question: Activity a m b Immediate Predecessor(s) Activity a m b Immediate Predecessor(s) A 6 8 12 - G 3 3 5 C, E B 1

Activity a m b Immediate Predecessor(s) Activity a m b Immediate Predecessor(s) A 6 8 12 - G 3 3 5 C, E B 1 9 24 A H 2 2 2 F C 9 12 18 A I 5 5 5 F D 5 7 10 A J 4 7 12 D, G, H E 1 3 4 B K 3 3 4 I, J F 6 9 20 C, E

A) The expected (estimated time for activity C is ___ weeks. (Round your response to two decimal places.)

B) The variance for activity C is ___ weeks. (Round your response to two decimal places.)

C) Based on the calculation of the estimated times, the critical path is _______.

D) The estimated time for the critical path is ___ weeks. (Round your response to two decimal places.)

E) The activity variance along the critical path is ___ weeks. (Round your response to two decimal places.)

F) The probability that Hopkins Hospitality will finish the project in 36 weeks or less is ____. (Enter as a probability and round your response to three decimal places.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!