Question: Description Activity a m b Activity Predecessor A 5 7 -- A 10 A WU 5 A 6 LO 12 B, C LO 15 D

Description Activity a m b Activity Predecessor A 5 7 -- A 10 A WU 5 A 6 LO 12 B, C LO 15 D Table ZZ Using Table ZZ, the variance of the project's total completion time is O A. 5.472 weeks. O B. 5.222 weeks. O C. 4.872 weeks. O D. 3.752 weeks