Question: Activity C on a CPM network has predecessor B , and has successors D and F . C has duration 7 days. B ' s

Activity C on a CPM network has predecessor B, and has successors D and F. C has duration 7 days. B's earliest finish is 20. D's late start is 30, while F's is 27. Which of the following is definitely TRUE?
D has no slack and is critical..
B has slack and is not critical.
C is completed before B.
C has no slack and is critical.
F has slack and is not critical.