Question: Activity C on a CPM network has predecessor B , and has successors D and F . C has duration 7 days. B ' s
Activity on a CPM network has predecessor and has successors and C has duration days. Bs earliest finish is Ds late start is while Fs is Which of the following is definitely TRUE?
D has no slack and is critical..
has slack and is not critical.
C is completed before
C has no slack and is critical.
F has slack and is not critical.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
