Question: Activity C on a CPM network has predecessor B, and has successors D and F.C has duration 7 days. B's earliest finish is 20. D's

Activity C on a CPM network has predecessor B, and has successors D and F.C has duration 7 days. B's earliest finish is 20. D's late start is 30 , while F's is 27 . Which of the following is definitely TRUE? F has slack and is not critical. D has slack and is not critical.. C is completed before B. B has slack and is not critical. C has slack and is not critical