Question: Activity C on a CPM network has predecessor B , and has successors D and F . C has duration 7 days. B ' s
Activity C on a CPM network has predecessor B and has successors D and F C has duration days. Bs earliest finish is Ds late start is while Fs is Which of the following is definitely TRUE?
Group of answer choices
D has no slack and is critical..
C is completed before B
F has slack and is not critical.
B has slack and is not critical.
C has no slack and is critical.