Question: Activity Duration (Days) Immediate Predecessor Optimistic Most likely Pessimistic 2 3 4 B A 4 6 8 C A 3 3 3 D A 5

Activity Duration (Days) Immediate Predecessor

Activity Duration (Days) Immediate Predecessor Optimistic Most likely Pessimistic 2 3 4 B A 4 6 8 C A 3 3 3 D A 5 7 9 E B, C 2 4 6 F C D 6 7 8 G D 3 4 8 H D 2 3 4 1 E, F, G 1 3 5 J F 3 5 7 K F, G 4 6 8 L H 6 8 13 M 2 5 8 N K, L, M 4 6 8 1. Draw the network diagram of the project. [5 marks] 2. Determine the critical path(s) of the project and calculate the project completion time. [5 marks] 3. Ider non-critical activity in the network and explain the meaning of the floats. [5 marks] or

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!