Question: Activity Duration (days) Predecessors A 3 B 2 6 6 A D 1 . TI 2 CD F 3 D G 4 EF a) How

Activity Duration (days) Predecessors A 3 B 2 6 6
Activity Duration (days) Predecessors A 3 B 2 6 6 A D 1 . TI 2 CD F 3 D G 4 EF a) How long will the entire project take? b) What is the critical path? C) What is the slack in task D? d) As the project manager, you know that the project has an overhead cost of $2000 per day. Any reduction in project duration would save this cost. The person doing task F says she can crash it by one day (from 3 days to 2 days) for an extra cost of $500. Should you tell her to do that? Why or why not