Question: Activity Duration Depends on A 4 B 2 C 5 A D 7 A,B E 6 B F 1 E G 4 D,E H 5

Activity Duration Depends on
A 4
B 2
C 5 A
D 7 A,B
E 6 B
F 1 E
G 4 D,E
H 5 F,G
I 2 F
J 3 C

a. Use the precedence table to draw an activity-on-arc network. Include the early and late times for each event. [8 ]

b. Which activities are critical [2 ]

c. Find the critical path for the network. [2 ]

d. Calculate the float of each activity [6 ]

e. What is the total float activity? [3 ]

f. Draw a Cascade (Gantt) charts to represent the project [5 ]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!