Question: Activity Duration Depends on A 4 B 2 C 5 A D 7 A,B E 6 B F 1 E G 4 D,E H 5
| Activity | Duration | Depends on |
| A | 4 | |
| B | 2 | |
| C | 5 | A |
| D | 7 | A,B |
| E | 6 | B |
| F | 1 | E |
| G | 4 | D,E |
| H | 5 | F,G |
| I | 2 | F |
| J | 3 | C |
a. Use the precedence table to draw an activity-on-arc network. Include the early and late times for each event. [8 ]
b. Which activities are critical [2 ]
c. Find the critical path for the network. [2 ]
d. Calculate the float of each activity [6 ]
e. What is the total float activity? [3 ]
f. Draw a Cascade (Gantt) charts to represent the project [5 ]
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts