Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A 4 - B
A project for improving a billing process has the following precedence relationships and activity times:
Activity Activity Time (weeks) Immediate Predecessor(s) A 4 - B 12 - C 5 A D 11 B, C E 10 B F 4 D G 7 E H 9 F, G
b. Calculate the slack for each activity. Which activities are on the critical path?
| Activity | Activity Time (weeks) | On critical path? | Slack (weeks) |
| A | 44 | No Yes | nothing |
| B | 1212 | Yes No | nothing |
| C | 55 | No Yes | nothing |
| D | 1111 | No Yes | nothing |
| E | 1010 | Yes No | nothing |
| F | 44 | Yes No | nothing |
| G | 77 | Yes No | nothing |
| H | 99 | Yes No | nothing |