Question: ACTIVITY DURATION PREDECESSOR A 6 - B 4.33 - C 5 A,B D 20 C E 11 C F 7 E G 12 C H

ACTIVITY

DURATION

PREDECESSOR

A

6

-

B

4.33

-

C

5

A,B

D

20

C

E

11

C

F

7

E

G

12

C

H

6

D,F,G

I

9

G,F

J

5

H

K

29.7

I,J

Draw the network diagram showing activity durations and identify the critical path duration