Question: ACTIVITY DURATION PREDECESSOR A 6 - B 4.33 - C 5 A,B D 20 C E 11 C F 7 E G 12 C H
| ACTIVITY | DURATION | PREDECESSOR |
| A | 6 | - |
| B | 4.33 | - |
| C | 5 | A,B |
| D | 20 | C |
| E | 11 | C |
| F | 7 | E |
| G | 12 | C |
| H | 6 | D,F,G |
| I | 9 | G,F |
| J | 5 | H |
| K | 29.7 | I,J |
Draw the network diagram showing activity durations and identify the critical path duration
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts