Question: Activity Duration ( weeks ) Dependency Resources Start 0 A 8 Start 4 B 2 Start 2 C 3 Start 3 D 1 0 A
Activity
Duration weeks
Dependency Resources Start A Start B Start C Start D A E AB F C G C H D I DEF J H K G L I,J M F
Draw a full project network including early starts, late finishes, and slack using the legend provided
What is the length of the project?
What kind of project is it likely to be What is the critical path?
Draw the Gantt chart
Assuming there are only resources available for the duration of this project, how can the schedule be best adjusted to level the resources? Describe the changes made marks
Provide a revised Gantt chart to reflect this resource availability