Question: Activity Duration ( weeks ) Dependency Resources Start 0 A 8 Start 4 B 2 Start 2 C 3 Start 3 D 1 0 A

Activity
Duration (weeks)
Dependency Resources Start 0 A 8 Start 4 B 2 Start 2 C 3 Start 3 D 10 A 2 E 8 A,B 4 F 8 C 3 G 2 C 4 H 5 D 5 I 9 D,E,F 2 J 6 H 4 K 5 G 3 L 4 I,J 5 M 4 F 3
Draw a full project network including early starts, late finishes, and slack using the legend provided
- What is the length of the project?
- What kind of project is it likely to be?- What is the critical path?
- Draw the Gantt chart
- Assuming there are only 10 resources available for the duration of this project, how can the schedule be best adjusted to level the resources? Describe the changes made (8 marks)
- Provide a revised Gantt chart to reflect this resource availability
 Activity Duration (weeks) Dependency Resources Start 0 A 8 Start 4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!