Question: Given the project table below: Activity Duration ( weeks ) Dependency Resources A 8 4 B 2 A 2 C 3 A 3 D 1

Given the project table below:
Activity Duration
(weeks) Dependency Resources
A 84
B 2 A 2
C 3 A 3
D 10 A 2
E 12 B 4
F 8 B 3
G 2 C 4
H 5 E 5
I 9 E,F,G 4
J 6 H 4
K 5 I,J 3
L 4 D,G,K 5
a) Draw a project network from the table above (10 marks)
b)
i. What activity(s) is a burst activity? (1 mark)
ii. What activity(s) is a merge activity? (1 mark)
iii. What is the length of the project? (1 mark)
iv. What is the critical path? (11/3 marks)
c) Draw the Gantt chart (6 marks)
d) Assuming there are only 10 resources available for the duration of this project, how can the
schedule be best adjusted to level the resources? List the changes made (8 marks)
e) Revise the Gantt chart to reflect this resource availability (5 marks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!