Question: Given the project table below: Activity Duration ( weeks ) Dependency Resources A 8 4 B 2 A 2 C 3 A 3 D 1
Given the project table below:
Activity Duration
weeks Dependency Resources
A
B A
C A
D A
E B
F B
G C
H E
I EFG
J H
K I,J
L DGK
a Draw a project network from the table above marks
b
i What activitys is a burst activity? mark
ii What activitys is a merge activity? mark
iii. What is the length of the project? mark
iv What is the critical path? marks
c Draw the Gantt chart marks
d Assuming there are only resources available for the duration of this project, how can the
schedule be best adjusted to level the resources? List the changes made marks
e Revise the Gantt chart to reflect this resource availability marks