Question: Activity durations (in weeks) for a project are given below: Activity Precedence Optimistic time Most likely time Pessimistic time Expected time Variance A - 6
Activity durations (in weeks) for a project are given below:
|
|
|
|
|
|
|
|
|
Activity | Precedence | Optimistic time | Most likely time | Pessimistic time | Expected time | Variance |
| A | - | 6 | 7 | 14 | 8.00 | 1.78 |
| B | - | 8 | 10 | 12 | 10.00 | 0.44 |
| C | - | 2 | 3 | 4 | 3.00 | 0.11 |
| D | A | 6 | 7 | 8 | 7.00 | 0.11 |
| E | B, C | 5 | 5.5 | 9 | 6.00 | 0.44 |
| F | B, C | 5 | 7 | 9 | 7.00 | 0.44 |
| G | D, E | 4 | 6 | 8 | 6.00 | 0.44 |
| H | F | 2.5 | 3 | 3.5 | 3.00 | 0.03 |
What is the probability that the project will finish 1 week early? Perform the necessary calculations and complete entries in the table below.
NOTE: Some rows in table below may be blank.
| Path | Probability finishing the project 1 week early | |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
|
|
|
|
|
|
Joint probability of completing the project 1 week early = _________