Question: What is the critical path? Activity Optimistic time Most likely time Pessimistic time Expected time Variance A 8 10 12 B 4 10 16 4
What is the critical path?

Activity Optimistic time Most likely time Pessimistic time Expected time Variance A 8 10 12 B 4 10 16 4 5 6 D 6 8 10 E 4 7 12 F 6 7 9 G 4 8 12 H 3 3 3 B(10) D(8) 17.17) A(10) H(3) 0(5) E(7.33) G(8) What is the critical path? What is the probability of completing the project (along the critical path) within 36 weeks? What is the probability of completing the project (along the critical path) within 40 weeks? By how many weeks are we 99% sure of completing the project (along the critical path)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
