Question: Activity ID Description Activity Predecesser Active Time(Weeks) A Staff None 2 B Develop market program A 2 C Select distribution channels A 8 D patent
| Activity ID | Description | Activity Predecesser | Active Time(Weeks) |
| A | Staff | None | 2 |
| B | Develop market program | A | 2 |
| C | Select distribution channels | A | 8 |
| D | patent | B,C | 20 |
| E | pilot production | B | 5 |
| F | test market | D,E | 4 |
| G | Ad promotions | F | 5 |
| H | Web promotions | F | 4 |
| I | set up for production | F | 16 |
| J | launch | G,H,I | 1 |
a. Draw a project network diagram using the Arrow on Node (AON) method.
On the diagram you just drew, do the following tasks: b. Complete the forward pass on your drawn network (0-5PTS) c. Complete the backward pass on your drawn network (0-5 PTS) d. Calculate the slack for each activity on the network early and late (2 PTS) e. Identify the critical path(s) using their IDs (3 PTS). f. Identify the PROJECT duration (3PTS) g Identify the IDs of the activities that present the following: (1 PT each) Concurrent or parallel activities Merge activities Burst activities