Question: Activity Immediate Predecessor(s) Te VAR Slack A - 5 0.444 0 B - 2 0.111 4 C - 3 0.444 6.5 D A 7.5 0.25

Activity Immediate Predecessor(s) Te VAR Slack A - 5 0.444 0 B - 2 0.111 4 C - 3 0.444 6.5 D A 7.5 0.25 0 E B 6.5 0.694 4 F C 8 0.111 6.5 G D, E 5 0.111 0 What is the critical path for the project described by this table? Part 2 A. C-F B. A-D-G C. B-E-G D. A-B-C