Question: Immediate Predecessor(s) Activity VAR Slack 0.444 0 2 0.111 4 3 0.444 6.5 - 7.5 0 0.25 0.694 6.5 4 8 0.111 6.5 D, E

Immediate Predecessor(s) Activity VAR Slack 0.444

Immediate Predecessor(s) Activity VAR Slack 0.444 0 2 0.111 4 3 0.444 6.5 - 7.5 0 0.25 0.694 6.5 4 8 0.111 6.5 D, E 0.111 0 What is the critical path for the project described by this table? O A. A-B-C O B. C-F O C. B-E-G OD. A-D-G