Question: Activity Immediate Predecessors Time in weeks N/A 3 B 5 A 6 D B, C 4 E 7 F B 8 G D, E 6

Activity Immediate Predecessors Time in weeks N/A

Activity Immediate Predecessors Time in weeks N/A 3 B 5 A 6 D B, C 4 E 7 F B 8 G D, E 6 H F, G 6 B F A H What is slack time for activity B? Answer: 3