Question: Activity Optimistic Time (Weeks) Most Likely Time ( weeks) Pessimistic Time (weeks) A 8 10 12 B 4 10 16 C 4 5 6 D

Activity Optimistic Time (Weeks) Most Likely Time ( weeks) Pessimistic Time (weeks)
A 8 10 12
B 4 10 16
C 4 5 6
D 6 8 10
E 4 7 12
F 6 7 9
G 4 8 12
H 3 3 3

1.What is the critical path?

2.What is the Expected Project Completion Time for the AON and table above?

3.What is the variance for the critical path?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!