Question: Activity Optimistic Time (Weeks) Most Likely Time ( weeks) Pessimistic Time (weeks) A 8 10 12 B 4 10 16 C 4 5 6 D
| Activity | Optimistic Time (Weeks) | Most Likely Time ( weeks) | Pessimistic Time (weeks) |
| A | 8 | 10 | 12 |
| B | 4 | 10 | 16 |
| C | 4 | 5 | 6 |
| D | 6 | 8 | 10 |
| E | 4 | 7 | 12 |
| F | 6 | 7 | 9 |
| G | 4 | 8 | 12 |
| H | 3 | 3 | 3 |
1.What is the critical path?
2.What is the Expected Project Completion Time for the AON and table above?
3.What is the variance for the critical path?