Question: Activity P Duration 2 days, Predecessor None. Activity Q Duration 5 days, Predecessor P . Activity R Duration 1 0 days, Predecessor Q . Activity

Activity P Duration 2 days, Predecessor None. Activity Q Duration 5 days, Predecessor P. Activity R Duration 10 days, Predecessor Q. Activity S Duration 13 days, Predecessor P. If there is a delay of 2 days in the completion of Activity Q, how does it affect the project?