Question: Activity P Duration 7 days, Predecessor None. Activity Q Duration 5 days, Predecessor P . Activity R Duration 1 0 days, Predecessor Q . Activity

Activity P Duration 7 days, Predecessor None. Activity Q Duration 5 days, Predecessor P. Activity R Duration 10 days, Predecessor Q. Activity S Duration 14 days, Predecessor P. If Activity Q finishes 2 days before schedule, how does it affect the project?
Question 8Answer
a.
Project duration increases by 1 day
b.
Project duration increases by 2 days
c.
Project duration remains unchanged
d.
Project duration decreases by 1 day
e.
Project duration decreases by 2 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!