Question: Activity P Duration 7 days, Predecessor None. Activity Q Duration 5 days, Predecessor P . Activity R Duration 1 0 days, Predecessor Q . Activity
Activity P Duration days, Predecessor None. Activity Q Duration days, Predecessor P Activity R Duration days, Predecessor Q Activity S Duration days, Predecessor P If there is a delay of days in the completion of Activity S how does it affect the project?
Question Answer
a
Project duration increases by day
b
Project duration remains unchanged
c
Project duration decreases by day
d
Project duration decreases by days
e
Project duration increases by days