Question: Activity X Duration 3 days, Predecessor None. Activity Y Duration 5 days, Predecessor X . Activity W Duration 4 days, Predecessor X . Activity Z

Activity X Duration 3 days, Predecessor None. Activity Y Duration 5 days, Predecessor X. Activity W Duration 4 days, Predecessor X. Activity Z Duration 7 days, Predecessor Y, W. If you want to minimize the project duration, which activity(ies) should you focus on shortening?