Question: Activity X Duration 3 days, Predecessor None. Activity Y Duration 5 days, Predecessor X . Activity W Duration 4 days, Predecessor X . Activity Z
Activity X Duration days, Predecessor None. Activity Y Duration days, Predecessor X Activity W Duration days, Predecessor X Activity Z Duration days, Predecessor Y W If you want to minimize the project duration, which activityies should you focus on shortening?