Question: ACTIVITY PREDECESSOR DURATION (DAYS) A - 3 B A 2 C A 4 D B,C 5 E B,C 2 F E 5 Find the Critical

ACTIVITY

PREDECESSOR

DURATION (DAYS)

A

-

3

B

A

2

C

A

4

D

B,C

5

E

B,C

2

F

E

5

  1. Find the Critical Path and Duration of this project

  1. Find the ES, EF, LS, LF for activities in the project

  1. Find the slack of each activity. Slack = LS-ES or LF-EF