Question: ACTIVITY PREDECESSOR DURATION (DAYS) A - 3 B A 2 C A 4 D B,C 5 E B,C 2 F E 5 Find the Critical
| ACTIVITY | PREDECESSOR | DURATION (DAYS) |
| A | - | 3 |
| B | A | 2 |
| C | A | 4 |
| D | B,C | 5 |
| E | B,C | 2 |
| F | E | 5 |
- Find the Critical Path and Duration of this project
- Find the ES, EF, LS, LF for activities in the project
- Find the slack of each activity. Slack = LS-ES or LF-EF