Question: Q2) Activity Predecessor Duration (days) A - 3 B A 4 C A 2 D B 5 E C 1 F C 2 G D,E
Q2) Activity Predecessor Duration (days) A - 3 B A 4 C A 2 D B 5 E C 1 F C 2 G D,E 4 H F,G 3
Perform critical path analysis by finding: a) Earliest start b) Latest start c) Earliest finish d) Latest finish e) Slack f) Critical path