Question: activity predecessor duration start A None 4 B A 8 C A 9 D B 3 E C 4 F D 6 G E,F 10
| activity | predecessor | duration |
| start | ||
| A | None | 4 |
| B | A | 8 |
| C | A | 9 |
| D | B | 3 |
| E | C | 4 |
| F | D | 6 |
| G | E,F | 10 |
| End |
Using the information provided in the following table, create a network diagram using the precedence diagram method and determine the duration of the project.Can you upload the network diagram that has been used to determine the duration of the project clearly indicating the critical path.