Question: activity predecessor duration start A None 9 B A 9 C A 2 D B 8 E C 9 F D 6 G E,F 2
| activity | predecessor | duration |
| start | ||
| A | None | 9 |
| B | A | 9 |
| C | A | 2 |
| D | B | 8 |
| E | C | 9 |
| F | D | 6 |
| G | E,F | 2 |
| End |
Using the information provided in the following table, create a network diagram using the precedence diagram method and determine the duration of the project. Ensure you keep the network diagram as it will need to be uploaded in the upload network diagram question.