Question: Activity Predecessor Duration (weeks) a none 12 b none 5 c a, b 7 d c, e 2 e b 8 f e 9 g
| Activity | Predecessor | Duration (weeks) |
| a | none | 12 |
| b | none | 5 |
| c | a, b | 7 |
| d | c, e | 2 |
| e | b | 8 |
| f | e | 9 |
| g | d | 5 |
| h | f,g | 8 |
Your firm is implementing a balanced scorecard. As the project manager, you need to make sure the project is completed on time and on-budget. The table below lists the steps that need to be complete. What is the critical path for this project?