Question: Activity Predecessor Duration (weeks) a none 12 b none 5 c a, b 7 d c, e 2 e b 8 f e 9 g

Activity Predecessor Duration (weeks)
a none 12
b none 5
c a, b 7
d c, e 2
e b 8
f e 9
g d 5
h f,g 8

Your firm is implementing a balanced scorecard. As the project manager, you need to make sure the project is completed on time and on-budget. The table below lists the steps that need to be complete. What is the critical path for this project?

Group of answer choices

A-C-D-G-H

B-E-D-G-H

B-C-D-G-H

There is more than one critical path

B-E-F-H