Question: PERT HOMEWORK #3 Design a PERT Chart based on the activities below and be sure to include the ECT, LAT, slack time for each node,
PERT HOMEWORK #3
Design a PERT Chart based on the activities below and be sure to include the ECT, LAT, slack time for each node, along with the critical path.
Activity Predecessor Duration (days)
A NONE 2
B A 5
C A 2
D NONE 4
E D 5
F D 5
G D 7
H B, C, E 2
I F, G 6
J H 4
K I, J 5
L G 5
M L 6