Question: PERT HOMEWORK #3 Design a PERT Chart based on the activities below and be sure to include the ECT, LAT, slack time for each node,

PERT HOMEWORK #3

Design a PERT Chart based on the activities below and be sure to include the ECT, LAT, slack time for each node, along with the critical path.

Activity Predecessor Duration (days)

A NONE 2

B A 5

C A 2

D NONE 4

E D 5

F D 5

G D 7

H B, C, E 2

I F, G 6

J H 4

K I, J 5

L G 5

M L 6