Question: Activity Predecessor Duration (weeks) a none 4 b none 5 c a, b 8 d c, e 6 e b 2 f e 9 g
| Activity | Predecessor | Duration (weeks) |
| a | none | 4 |
| b | none | 5 |
| c | a, b | 8 |
| d | c, e | 6 |
| e | b | 2 |
| f | e | 9 |
| g | d | 7 |
| h | f,g | 4 |
Your firm is working on a Sales and Operations improvement project. As the project manager, you need to make sure the project is completed on time and on-budget. The table below lists the steps that need to be complete. What is the length of the project?
Your firm is working on a Sales and Operations improvement project. As the project manager, you need to make sure the project is completed on time and on-budget. The table below lists the steps that need to be complete. Which activity has the MOST slack time?