Question: Activity | Predecessor | Duration (weeks) A2B4CA3DB6EB5FC,D4GE,F7 What is the critical path of the project, and how long will it take to complete? Select one:

Activity | Predecessor | Duration (weeks) A2B4CA3DB6EB5FC,D4GE,F7 What is the critical path of the project, and how long will it take to complete? Select one: Critical Path: A - C - F - E - G; Total Duration: 18 weeks Critical Path: A - C - D - F - G; Total Duration: 19 weeks Critical Path: A - C - F - G; Total Duration: 16 weeks Critical Path: A - C - D - F - E - G; Total Duration: 20 weeks Clear my choice