Question: Activity Predecessor Optimistic Probable Pessimistic A - 5 11 14 B - 3 3 9 C - 6 10 14 D A, B 3 5
| Activity | Predecessor | Optimistic
| Probable | Pessimistic
|
| A | - | 5 | 11 | 14 |
| B | - | 3 | 3 | 9 |
| C | - | 6 | 10 | 14 |
| D | A, B | 3 | 5 | 7 |
| E | B | 4 | 6 | 11 |
| F | C | 6 | 8 | 13 |
| G | D, E | 2 | 4 | 6 |
| H | F | 3 | 3 | 9 |
By using evaluating and reviewing the project answer the following questions:
- Calculate the expected time to finish the project?
- What is the probability to finish the project in less than 28 days?