Question: Activity Predecessor Optimistic Probable Pessimistic A - 5 11 14 B - 3 3 9 C - 6 10 14 D A, B 3 5

Activity

Predecessor

Optimistic

Probable

Pessimistic

A

-

5

11

14

B

-

3

3

9

C

-

6

10

14

D

A, B

3

5

7

E

B

4

6

11

F

C

6

8

13

G

D, E

2

4

6

H

F

3

3

9

By using evaluating and reviewing the project answer the following questions:

  1. Calculate the expected time to finish the project?
  2. What is the probability to finish the project in less than 28 days?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!