Question: Activity Predecessor(s) Duration (days) A --- 5 B A 20 C A 15 D A 5 E B, C 60 F D 15 G E
| Activity | Predecessor(s) | Duration (days) |
| A | --- | 5 |
| B | A | 20 |
| C | A | 15 |
| D | A | 5 |
| E | B, C | 60 |
| F | D | 15 |
| G | E | 20 |
| H | E | 15 |
| I | F, G, H | 2 |
Consider the network scheduling data presented in the table above. How many days of slack are associated with activity F?
| 88 | ||
| 80 | ||
| 12 | ||
| 15 |