Question: Activity R on a CPM network has predecessors M and N , and has successor S . R has duration 5 . N ' s
Activity R on a CPM network has predecessors M and N and has successor S R has duration Ns late finish is while Ms is Ss late start is Which of the following is definitely true?
is a critical activity.
is a critical activity.
is critical and has zero slack.
has no slack but is not critical.
The set of times cannot all be possible.
Who is responsible for the success and failure of a project?
the CEO
the program manager
the project manager
the project sponsor
the functional manager