Question: Activity R on a CPM network has predecessors M and N , and has successor S . R has duration 5 . N ' s

Activity R on a CPM network has predecessors M and N , and has successor S . R has duration 5. N's late finish is 18, while M's is 20. S's late start is 14. Which of the following is definitely true?
N is a critical activity.
S is a critical activity.
R is critical and has zero slack.
R has no slack but is not critical.
The set of times cannot all be possible.