Question: Activity D on a CPM network has predecessors B and C, and has successor F. Activity time for D is 9. Earliest finish time of
Activity D on a CPM network has predecessors B and C, and has successor F. Activity time for D is 9. Earliest finish time of B is 12 and earliest finish time of C is 20. Latest start time of F is 38. Write down the slack for F.