Question: Adjust your analysis to the information in the table without modifying the baseline information. Analyze the project execution time following the PERT Diagram methodology. Establish

Adjust your analysis to the information in the table without modifying the baseline information. Analyze the project execution time following the PERT Diagram methodology. Establish Critical Path of the project. Set the duration of the work. Complete the table.

ACTIVITY DESCRIPTION PREDECESSOR DURATION (DAYS) Earliest Time Latest Time
A PRELIMINARY WORK - 10
B DESIGN AND APPROVAL A 30
C STUDIES AND COSTS A 8
D CARRYING OUT THE PROJECT B,C 60
E TESTS D 10
F INSPECTION E 3
G PROJECT DELIVERY F 8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!