Question: Adjust your analysis to the information in the table without modifying the baseline information. Analyze the project execution time following the PERT Diagram methodology. Establish
Adjust your analysis to the information in the table without modifying the baseline information. Analyze the project execution time following the PERT Diagram methodology. Establish Critical Path of the project. Set the duration of the work. Complete the table.
| Activity | Description of Activity | Predecessor | Duration | Earliest Time | Latest Time |
| A | Construction Permit | - | 3 | ||
| B | Mobilization | A | 2 | ||
| C | Topography | A | 4 | ||
| D | Wall Type A | B, C | 12 | ||
| E | Wall Type B and C | B,C | 45 | ||
| F | Foundations | B,C | 20 | ||
| G | Electricity | F | 6 | ||
| H | Structure | D,G | 22 | ||
| I | Touch-Ups | H | 30 | ||
| J | Roof | H | 10 | ||
| K | Paint | I | 18 | ||
| L | Trials and Delivery | E,K | 3 | ||