Question: After completing Lab # 4 , answer the following questions from the schedule printouts and turn the Schedule Analysis - Lab # 4 in to
After completing Lab # answer the following questions from the schedule printouts and turn the Schedule Analysis Lab # in to your instructor stapled on top of your schedule printouts.
Network Diagram View:
Is there a timescale shown on this schedule? Yes No
What potential task information is displayed inside each task box list each
Calendar View:
Is the critical path visible Yes No
Is the Project Summary Task visible? Yes No
Critical Task Group View:
Is the Critical Task Group a custom group Yes No
Task Calendar Task Group View:
Why is the Project Summary Task not at the top of the schedule?
Are the tasks connected graphically together across different groups? Yes No Custom Task Group View:
Are the tasks within each group sorted primarily by circle one Task ID or Early Start
Which group is the primary sort circle one Contractor or Responsibility
Summary Task View:
How is the duration of the summary tasks derived?
All Views:
Did the critical path change when changing from one view to the next? Yes No
Which view is different from the others listed in the way that it is created in the software circle one Critical Task Calendar Custom Summary
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock