Question: After completing the Gantt chart for a project, Katherine assigned different levels of responsibility to members of the project team and to some of the
After completing the Gantt chart for a project, Katherine assigned different levels of responsibility to members of the project team and to some of the project stakeholders. She noted that the company CEO wanted final approval on all wardrobe choices for the models, even though the marketing team came up with the vision and design for each clothing shoot. Katherine's RACI will include the project sponsor and the marketing team. Although the marketing team is the video shoot design elements, the CEO is the wardrobe selection. a.) consulted about; responsible for b.) informed about; accountable for c.) responsible for; accountable for ( d.) accountable for; responsible for