Question: am (Chapters 1,2,3, 5 - 7) i Saved Schedule the following activities using CPM: IMMEDIATE PREDECESSOR TIME (WEEKS) 2 5 ACTIVITY A B c D

am (Chapters 1,2,3, 5 - 7) i Saved Schedule theam (Chapters 1,2,3, 5 - 7) i Saved Schedule the

am (Chapters 1,2,3, 5 - 7) i Saved Schedule the following activities using CPM: IMMEDIATE PREDECESSOR TIME (WEEKS) 2 5 ACTIVITY A B c D E F G H A A B C D D F EG 9 5 3 6 b. What is the critical path? O A-B-E-H O A-B-D-E-H O A-C-E-H O A-C-E-F-G-H c. How many weeks will it take to complete the project? Number of weeks d. Which activities have slack, and how much? OB. 3 weeks :D . 2 weeks