Question: Schedule the following activities using CPM: Immediate Predecessor Time (Week) 4 3 Activity A B C D E F G H A A B CD

Schedule the following activities using CPM: Immediate Predecessor Time (Week) 4 3 Activity A B C D E F G H A A B CD D F E, G 5 NN 3 For your convenience, a partially completed CPM diagram is provided. 1 5 D (2) F (2) G (2) 1 0 A(1) HO) TE 0 ni 4 f C (3) E (5) How many weeks will it take to complete the project? (Enter only a number, e.g., 12 weeks --> 12)