Schedule the following activities using CPM:

Schedule the following activities using CPM: IMMEDIATE PREDECESSOR TIME (WEEKS) D1 Inmou) Nontot-EN Requirement 1: What is the critical path? A-B-D-E-H Requirement 2: How many weeks will it take to complete the project? Number of weeks 16 Requirement 3: Which activities have slack? (Click to select)