Question: Schedule the following activities using CPM: Immediate Predecessor Time (Week) Activity A B 4 A E SF C D D F EG For your convenience,

Schedule the following activities using CPM:

Schedule the following activities using CPM: Immediate Predecessor Time (Week) Activity A B 4 A E SF C D D F EG For your convenience, a partially completed CPM diagram is provided. 1 5 B (4) 0 (2) F (2) G (2) 1 5 0 1 H (3) A (1) C (3) E (5) 4 Question 17 Not yet answered Points out of 1.00 P Flag question How many weeks will it take to complete the project? (Enter only a number, e.g., 12 weeks --> 12)