Question: Schedule the following activities using CPM: IMMEDIATE PREDECESSOR TIME (WEEKS) 4 ACTIVITY A B D E F C D D F EG mm N 5

Schedule the following activities using CPM:
Schedule the following activities using CPM:
Schedule the following activities using CPM: IMMEDIATE PREDECESSOR TIME (WEEKS) 4 ACTIVITY A B D E F C D D F EG mm N 5 4 2 b. What is the critical path? O A-B-D-F-G-H O A-C-E-G-H O A-B-D-E-H O A-C-E-F-G-H c. How many weeks will it take to complete the project? Number of weeks d. Which activities have slack, and how much? OB 2 weeks :D , 1 week. OE. 3 weeks iH, 2 weeks. O C. 10 weeks: E. 6 weeks