Question: An activity on a PERT network has the following time estimates: optimistic = 9, most likely = 18, and pessimistic = 26. Its standard deviation

An activity on a PERT network has the following time estimates: optimistic = 9, most likely = 18, and pessimistic = 26. Its standard deviation is? (two decimal places)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!