Question: An activity on a PERT network has these time estmates: optimistic =2, most likely =5, and pessimistic = 8 What is its expected activity time?

An activity on a PERT network has these time
An activity on a PERT network has these time estmates: optimistic =2, most likely =5, and pessimistic = 8 What is its expected activity time? A. 5.67 B. 5.00 C. 10.67 D. 3000 E. 5.33

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock