Question: An assembly line has three work stations A,B and C.The materials move from A to B and then to C. Station A takes 3 minutes,
An assembly line has three work stations A,B and C.The materials move from A to B and then to C. Station A takes 3 minutes, B 6 minutes and C 1 minute.
What is the cycle time (in minutes)?
a. 1
b. 3
c. 6
d. 10